Timeline

2010

Common User Facility (CUF) Hardstand Stage 1 (2 hectares)

2015

Common User Facility Hardstand Stage 2 (7 hectares)

Defence and LDC execute a design and construction agreement for the Barge Ramp

2016

Opening of the CUF Barge Ramp

NT Government selects preferred Ship Lift site

2017

Marine Service Area (5 lot subdivision for vessel workshops and services) commence planning and design

2018

Marine Service Area - Subdivision Development Permit issued for Stage 1

2019

Establishment of Regional Maintenance Centres announced by Defence

The Northern Australia Infrastructure Facility (NAIF) approves funding for $300M for Ship Lift

2020

Ship Lift planning and design

Development Permit - Marine Industry Park Serviced Lots - Stage 1

2021-2022

Marine Industry Park Hardstand Servicing and Expansion Investigations

Marine Industry Park Traffic Study

2021-2024

Ship Lift detailed design and construction

2024

May - Ship lift construction commencement

Q2 - Precincts 2 & 3 Strategic Business Case completed

Q4 – Release of tender for Precinct 1 subdivision construction works to create 11 industrial lots

2025

Q2 – Commencement of subdivision works for Precinct 1

Ship lift construction continues

2025-2026

Ship lift expected to be operational