Timeline
2013
Land Development Corporation submitted notice of intent to NT EPA
NT EPA advised no further environmental assessment required of Truck Central
2014
Expressions of Interest process for Truck Central developer
2015
Commencement of bulk earthworks commenced
2017
Truck Central subdivision works commence
2018
Upgrade works to Wishart and Kirkland Road intersection commence
BP Australia (BP) purchase Truck Stop site near the entrance of Truck Central
Road Train Assembly Area construction commenced and completed
Construction of Vehicle Inspection Faclility commenced and completed
2019
BP Truck Stop construction complete and open
Truck Central opened by Minister Lawler and open to the public
The Truck Central project recieved an award for excellence in civil construction at the 2019 Northern Territory Civil Contractor’s Federation Earth Awards.
2020
LDC commenced concept design of Wishart Stage 2 following interest from a potential purchaser
Stage 2 subdivision design approved - Development Ready