2013

Land Development Corporation submitted notice of intent to NT EPA

NT EPA advised no further environmental assessment required of Truck Central

2014

Expressions of Interest process for Truck Central developer

2015

Commencement of bulk earthworks commenced

2017

Truck Central subdivision works commence

2018

Upgrade works to Wishart and Kirkland Road intersection commence

BP Australia (BP) purchase Truck Stop site near the entrance of Truck Central

Road Train Assembly Area construction commenced and completed

Construction of Vehicle Inspection Faclility commenced and completed

2019

BP Truck Stop construction complete and open

Truck Central opened by Minister Lawler and open to the public

The Truck Central project recieved an award for excellence in civil construction at the 2019 Northern Territory Civil Contractorā€™s Federation Earth Awards.

2020

LDC commenced concept design of Wishart Stage 2 following interest from a potential purchaser

Stage 2 subdivision design approved - Development Ready